When tackling high-stakes infrastructure projects, speed, precision, and cost efficiency are critical. Our recent work on a major industrial project is a perfect example of how strategic planning and expert execution can significantly impact a construction timeline.
Rapid Turnaround: From Order to Installation in Two Weeks
From the moment the order was placed, our team had just two weeks to design, manufacture, and deliver a highly customized conduit solution. The project included:
β 10 custom stub-up products
β Over 340 offset conduits
β Primarily 4β galvanized rigid conduit
Overcoming Complex Challenges
The success of this project hinged on navigating key challenges:
πΉ Site-Specific Coordination β Ensuring accurate depths based on site conditions and existing trenches.
πΉ Precision in Placement β Every conduit had to be measured and aligned precisely for the post-concrete foundation pour.
πΉ Budget & Schedule Constraints β Material costs had to be minimized while keeping the fast-track construction schedule intact.
Innovative Solutions for Maximum Efficiency
To meet these challenges head-on, our team implemented a proactive approach:
β
Pre-Coordinated Stub-Ups β All stub-up assemblies were designed and finalized before arriving on site, streamlining installation.
β
Pre-Manufactured Offsets β Over 340 conduit offsets were fabricated and strapped in place for an effortless drop into existing trenches.
β
Significant Time & Labor Savings β Our approach shaved weeks off the construction schedule and delivered 20% labor cost savings.